71、When performing project activity duration estimates, ( ) is not included in the estimation techniques.
A、Three-point EstimatingB、Analogous Estimating
C、Parametric EstimatingD、Checklist Estimating
72. Self-driving technologies are important for the research and development in the field of ( )。
A、Cloud ComputingB、Digital Finance
C、Artificial IntelligenceD、Intelligent Manufacturing
73、To build a modern logistics system,we should work on the ( ) of its infrastructure, including railways and ports, and promote the integration of sources in the sector.
A、digital transformation
B.new generation of communication technology
C、block-chain technology
D.VR and AR
74、Information security emphasizes the security attributes of information(data) itself.( ) is not included in the security attributes.
A、ConfidentialityB、ConsistencyC、IntegrityD、Availability
75、()is enforced in 2021。
A、The Civil Code of the People's Republic of China
B、The Tendering and Bidding Law of the People's Republic of China
C、Government Procurement Law of the People's Republic of China.
D、The Personal Information Protection Law of the People's Republic of China
【2024年第1批】
71. ( ) uses the data and results from the ( ) process to reflect the overall quality status of the project to the stakeholders.
A. Control Quality; plan quality management
B. Plan Quality Management; manage quality
C. Manage Quality; control quality
D. Control Quality; manage quality
72、How frequently the risks are being reviewed, this should recorded in ().
A. Risk Management PlanB. issue Log
C. Risk RegisterD. Risk Report
73. Project Communications Management consists of two parts. The first part is developing a strategy to ensure communication is effective for stakeholders. The second part is carrying out the activities necessary to implement the ().
A. communication toolsB. communication technology
C. communication costD. communication strategy
74、( ) is the process of specifying the approach and identifying potential sellers.
A. Plan Procurement Management
B. Close Procurement Management
C. Control Procurement
D. Conduct Procurement
75、The project manager should use() tool for the purpose to report on the work remaining for projects.
A. cumulative flow diagramB. burn down chart
C. forecast estimationD. earned value
【2024年第2批】
48、Security vulnerability are considered a type of( )。
A. technical riskB. management risk
C. organizational riskD. commercial risk
54、( )is the basis of information.
A. DataB. wisdomC. conceptsD. knowledge
57、A project is a ( ) endeavor undertaken to create a unique product,service or result.
A. staticB. permanentC. temporaryD. renting
69. ()is based on Chat-GPT4.
A. Large Language Model B. Digital Twin
C. Meta-VerseD. Digital Transformation
70. ( ) is the correct full name for the OPM.
A. Organizational Project Management
B. Operational Performance Management
C. Optimized Portfolio Management
D. Outcome Performance Management
【2025年第1批】
73.The key technologies of ( ), mainly involve machine learning, natural language processing, expert systems and other technologies.
A. Virtual reality B. Big data
C. Artificial intelligence D. Cloud computing
74. ( ) is a method used to create and evolve the product, service, or result during the project life such as a predictive, incremental, adaptive, or hybrid method.
A. Project Analysis Approach B. Project Phase
C. Project Deliverable D. Development Approach
75. The Perform Integrated Change Control process is conducted from project inception through completion and is the ultimate responsibility of the ().
A. change control board B. project management office
C. project manager D. configuration management office
【2025年第2批】
71.() is the process of identifying and documenting relationships among the project activities.
A. Sequence activitiesB. Estimate activity durations
C. Develop scheduleD. Define activities
72.() is the process of developing options, selecting strategies, and agreeing on actions to address overall project risk exposure, as well as to treat individual project risks.
A. Plan risk responsesB. Plan risk management
C. Implement risk responses D. Perform quantitative analysis
73. The main function of the ( ) process is to describe the boundaries and acceptance criteria of a product, service, or outcome.
A. Plan Scope ManagementB. Define Scope
C. Validate ScopeD. Control Scope
74. If the scope of work is well-defined and the project design has detailed specifications, ( ) should be used.
A. Fixed-Price ContractB. Time and Material Contract
C. Cost-Reimbursable ContractD. Cost Plus Incentive Fee
75. Configuration management is focus on the specification of both the deliverable and the process; While () is focused on identifying, documenting, and approving or rejecting changes to the project documents, deliverable, or baselines.
A. cost managementB. change management
C. configuration management D. capacity management
【2026年第1批】
26、 () is a iterative and incremental approach to deliver value to customer in short cycles.
A. Waterfall B. AgileC. PrototypeD. Spiral
57、Which of the following belongs to negative risk response strategy?
A. Exploit B. Enhance C. AvoidD. Share
66. () describes how project scope will be defined, validated and controlled.
A. Project charter B. Scope Management Plan
C. WBS D. Risk plan
75. Risk appetite refers to the () of an organization to accept risk.
A. Ability B. Willingness C. Limit D. Threshold
【2026年第2批】
2.()is set aside to address known uncertainties and implement risk response plans.
A. Project Fund B. Management Reserve
C. Contingency ReserveD. Operational Expense
14.()measures the degree to which a stakeholder (usually the customer) is willing to recommend a product or service to others,and serves as an indicator of customer loyalty.
A.Net Promoter Score (NPS)净推荐值
B. Return on Investment (ROI)
C. Cost Performance Indicator(CPI)
D. Key Performance Indicator(KPI)
27.()is an uncertain event or condition that,if it occurs,has a positive or negative effect on one or more project objectives.
A. Problem B. ChangeC. RiskD. Issue